Here is the tentative timeline for the redevelopment of the former Willow Grove military base: Jan. 15: Horsham Land Redevelopment Authority (HLRA) submits Economic Development Conveyance application to Navy.
Here is the tentative timeline for the redevelopment of the former Willow Grove military base:
Jan. 15: Horsham Land Redevelopment Authority (HLRA) submits Economic Development Conveyance application to Navy.
Jan.-March 2014: Public comment on Navy Environmental Impact Statement (EIS).
Spring 2014: HLRA interviews developers
Spring 2014: Navy records final EIS.
Summer 2014: Navy and HLRA negotiate land price.
After negotiations are complete, it will take at least four months to create deeds and go to settlement.
*Source: Matrix Design Group Economic Development Conveyance presentation, Dec. 18, 2013.