Low gear for Toyota, Honda
TOKYO - Toyota Motor Corp. said Friday that it would maintain output at half capacity in Japan from May 10 through June 3 because of a supply crunch for auto parts after the March 11 earthquake and tsunami disaster.
TOKYO - Toyota Motor Corp. said Friday that it would maintain output at half capacity in Japan from May 10 through June 3 because of a supply crunch for auto parts after the March 11 earthquake and tsunami disaster.
The world's No. 1 automaker said it remained unclear when it would return to full production in Japan. Toyota spokeswoman Shiori Hashimoto said the company was struggling to obtain about 150 types of auto parts.
The magnitude-9.0 earthquake and ensuing tsunami destroyed parts factories in northeastern Japan, causing severe supply shortages for Toyota and other automakers.
The twin disasters have caused Toyota a production loss of 260,000 cars, Hashimoto said.
Separately Friday, Honda Motor Co. said it would slow production at its 10 U.S. and Canadian auto factories through at least May 6 because it was running short of parts made at earthquake-damaged factories in Japan. The slowdowns, which could reduce output at its plants by up to 50 percent, are likely to cause shortages of Honda vehicles in a matter of weeks. Honda's Japanese factories are running at half capacity.
Toyota has shut down all output in Japan except at three plants, which are running at limited capacity to produce the Prius, two Lexus hybrids, and Corolla vehicles.
The company will resume production at all of its Japanese plants at half capacity from April 18 through 27, and then halt output from April 28 to May 9, a period that includes Golden Week holidays, when factories would normally close.
Limited output will resume at the plants from May 10 to June 3. Hashimoto said Toyota would later decide on production plans after June 6.
Masataka Kunugimoto, an auto analyst at Nomura Securities, said Toyota would likely incur an operating loss of 328 billion yen ($3.9 billion) in the April-June quarter because of the fallout from the post-tsunami parts shortage.
Toyota is again expected to post an operating loss of 78 billion yen ($938 million) in the July-September quarter, he said.
But the analyst forecast that Toyota's Japanese production would return to full capacity in September and that the company would swing back to the black later in the year.