Corzine decries Delaware River dredging deal

Gov. Corzine threatened today to delay the Delaware River ship channel deepening project, saying that the deal signed Monday violates his 2007 peace treaty with Gov. Rendell.

Gov. Corzine threatened today to delay the Delaware River ship channel deepening project, saying that the deal signed Monday violates his 2007 peace treaty with Gov. Rendell.

On Monday, port officials said the $379 million dredging project could begin within 10 months.

Corzine said his 2007 agreement with Rendell, which ended New Jersey's long and bitter efforts to halt the project, requires that his Department of Environmental Protection get to review the dredged material disposal plan and an updated environmental impact statement.

Corzine said it also appears that the Army Corps of Engineers plans to dump some dredged material in New Jersey, in violation of his agreement with Rendell.

"This position is totally unacceptable," Corzine wrote in a strong letter to John Paul Woodley Jr., the assistant secretary of the Army who signed the agreement with Pennsylvania. New Jersey will "take whatever measures are necessary" to enforce the 2007 agreement, the letter said.

Rendell responded to news of Corzine's letter by saying, in a statement, that "after over 15 years of study, the Army Corps and Philadelphia Regional Port Authority are proceeding with the project - I believe that is very good news for the ports of Pennsylvania and South Jersey."

He expressed confidence that the project would be carried out in an environmentally responsible manner and pledged to work with Corzine and others "to pursue beneficial uses" for the dredged material.

Khaalid Walls, deputy public affairs officer for the Army Corps of Engineers' Philadelphia District, said, "We just received the letter and are drafting a response, which will be complete next week."

Under the agreement signed Monday, to cheers of maritime executives and sign-waving union members, 102 miles of the river's ship channel, from Camden's Beckett Terminal to the ocean, would be deepened five feet, to 45 feet.

This would allow larger ships now being built to use terminals on the river and eliminate costly delays experienced by larger ships that can move only at high tide. Rendell predicted Monday that there would be "an avalanche of interest" from private firms wanting to invest in expanding the port as soon as channel-deepening commences.

At the ceremony Monday, Woodley pledged to seek beneficial uses for the dredged materials, such as reclaiming strip mines and providing raw material for manufactured topsoil.

But there is no formal dredge spoil disposal plan and Corzine said this also violates his agreement with Rendell. "It would be unfortunate," Corzine wrote, "for a federal agency to preempt such a cooperative agreement forged between two states."

The two-state dispute over the project brought to a crawl the workings of the bistate Delaware River Port Authority, which was to have been local sponsor of the project. The May 2007 agreement between the two governors ended the dispute.