Phillies installed artificial turf at FDR Park field without environmental permit, record shows

The field was completed in time for the Major League Baseball All-Star Game in July.

Work being conducted in June as Major League Baseball and the Philadelphia Phillies renovated Ashburn Field in FDR Park, a city field managed and maintained by the Phillies that hosts a variety of youth baseball programs. The new artificial turf field was unveiled in July.
Work being conducted in June as Major League Baseball and the Philadelphia Phillies renovated Ashburn Field in FDR Park, a city field managed and maintained by the Phillies that hosts a variety of youth baseball programs. The new artificial turf field was unveiled in July. Read moreColin Evans / For The Inquirer

The Philadelphia Phillies installed artificial turf at Ashburn Field in FDR Park in July but still have not obtained a required state permit, according to Pennsylvania Department of Environmental Protection records.

Major League Baseball and Phillies Charities Inc. held a ribbon-cutting for the renovated field, named after Hall of Famer Richie Ashburn, on July 10. It was part of festivities leading up to the MLB All-Star Game.

The renovation of the decades-old field included removing natural grass in favor of a “high-performance synthetic turf system and upgraded drainage” at the five-acre complex, according to an MLB news release.

However, documents from the Pennsylvania Department of Environmental Protection (DEP) show that the Phillies never obtained the required permit designed to address erosion control and stormwater release at the site.

Under Pennsylvania law, anyone disturbing more than one acre of ground is required to obtain a permit for stormwater discharges before beginning the work and explain how the work will affect drainage going forward.

DEP spokesperson Robyn Briggs said in an e-mailed statement that the agency is “currently reviewing the Phillies’ permit application and the compliance situation at the site. Because this matter is still under review, DEP cannot comment on whether any enforcement action or penalty will be taken.”

The permit review is listed as “paused,” the statement said, because the DEP is still waiting for the Phillies to address outstanding issues.

“Once the necessary information is received, DEP can continue its review,” the statement said.

City approval?

Bonnie Clark, a spokesperson for the Phillies, said in an e-mailed statement that “the recent upgrades to Richie Ashburn Field were undertaken in coordination with the city and relevant governmental agencies.”

Clark said the city authorized the work to proceed while permit applications were in process so the upgraded field could host All-Star Week events.

“We expect to obtain all necessary final approvals as early as next week,” Clark said.

Clark did not specify who at the city, or what department, the Phillies were working with. City officials did not respond to requests for comment.

When asked if this was proper procedure, Briggs reiterated that the DEP is “reviewing the compliance situation at the site” and noted the state law that requires the stormwater permit for construction-related earth disturbance.

Typically, state law supersedes city authority.

What is Ashburn Field?

Ashburn Field was part of an investment MLB made in Philadelphia’s youth baseball community for the 1996 All-Star Game. The field, owned by Philadelphia as part of its park system, is managed by the Phillies. It is the first large turf field installed at FDR Park.

MLB said the newly renovated field will serve about 8,000 participants in the Phillies Reviving Baseball in Inner Cities and Youth Academy programs, “while providing a weather-resistant playing surface in an area where rain often forces cancellations.”

‘Deficient’

The Phillies notified the DEP they were applying for a permit on May 13.

On May 27, the DEP sent a letter to the Phillies notifying the team that it needed additional information and logged 32 items that needed to be addressed, according to documents obtained by The Inquirer. That letter noted that final plan drawings had not been submitted, other drawings failed to include the project’s boundary, and not all water discharge areas were noted.

A local engineering firm hired by the Phillies responded in June to each point.

On July 7, the DEP sent another letter to the Phillies again noting technical deficiencies. And it sent another letter on July 24, about two weeks after the ribbon cutting, noting an outstanding deficiency and telling the Phillies to resubmit information in coordination with the Philadelphia Water Department.

The permit is still listed as pending on the DEP website.

The fight against artificial turf at FDR Park

Adding artificial turf to Ashburn Field is the latest in a yearslong debate about changes to FDR Park.

In 2019, the city’s parks and recreation department released a master plan to overhaul FDR Park, including the installation of 12 artificial turf fields in the footprint of a former golf course. (Those fields are separate from Ashburn Field.)

The department said average rainfall left sections of the park unusable for days because of frequent flooding. Officials predicted that flooding would only worsen because of climate change and said artificial turf fields would provide better flood control. The plan would require cutting down dozens of trees.

But that was pre-pandemic.

As COVID restrictions shut down the world, the golf course returned to a wild state and became a beloved space by dog owners, hikers, and birders. They nicknamed the space “the Meadows.”

Local opposition to the city’s plan grew, with critics objecting to the use of artificial turf amid natural lands. A grassroots group of South Philadelphians formed the Coalition to Save the Meadows, which has been vocal in its efforts to stop the park overhaul.

At the same time, the fields drew support from youth athletic clubs.

In March 2024, 11 South Philly residents filed suit calling for a stop on all work across FDR Park.

In May, Orphans’ Court Judge Sheila Woods-Skipper denied the critics’ request to temporarily stop work on the park as the trial played out.

» READ MORE: Critics of FDR Park’s renovation to appeal court decision after a blow to their case

In a recent social media post, the Coalition to Save the Meadows asked why the Phillies were allowed to move forward on Ashburn Field without the permit.

“PA DEP regulations and permitting requirements exist for a reason: to protect our waterways, watershed, and the people and wildlife that depend on them,” the post read. “So how was this project allowed to move forward without a permit — and will there be consequences?”

A legacy of artificial turf

Although Citizens Bank Park, the home of the Phillies, has a natural grass field, the team is no stranger to artificial turf.

The Inquirer reported in 2023 that six former members of the Phillies who played on the artificial turf field at the former Veterans Stadium died of brain cancer.

The article noted that the death of former Phillie David West in 2022 came at a time when there was growing scientific concern about the perils of PFAS, known as “forever chemicals” because of their resistance to breaking down.

PFAS were used to make the AstroTurf that was used at Veterans Stadium. The Vet opened in 1971 and was demolished in 2004.